Capacity Curtailment on the AT-IT border for delivery 04-01-2024

Published:

1. TSO(s)*:
TERNA-APG

2. Identification of affected Long Term Transmission Rights:

AT-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

04-01-2024 00:00 - 01:00 372 MW

04-01-2024 01:00 - 02:00 372 MW

04-01-2024 02:00 - 03:00 372 MW

04-01-2024 03:00 - 04:00 372 MW

04-01-2024 04:00 - 05:00 372 MW

04-01-2024 05:00 - 06:00 372 MW

04-01-2024 06:00 - 07:00 372 MW

04-01-2024 07:00 - 08:00 372 MW

04-01-2024 08:00 - 09:00 372 MW

04-01-2024 09:00 - 10:00 372 MW

04-01-2024 10:00 - 11:00 372 MW

04-01-2024 11:00 - 12:00 372 MW

04-01-2024 12:00 - 13:00 372 MW

04-01-2024 13:00 - 14:00 372 MW

04-01-2024 14:00 - 15:00 372 MW

04-01-2024 15:00 - 16:00 372 MW

04-01-2024 16:00 - 17:00 372 MW

04-01-2024 17:00 - 18:00 372 MW

04-01-2024 18:00 - 19:00 372 MW

04-01-2024 19:00 - 20:00 372 MW

04-01-2024 20:00 - 21:00 372 MW

04-01-2024 21:00 - 22:00 372 MW

04-01-2024 22:00 - 23:00 372 MW

04-01-2024 23:00 - 24:00 372 MW

5. Amount of LTTR remaining after curtailment:

04-01-2024 00:00 - 01:00 234 MW

04-01-2024 01:00 - 02:00 214 MW

04-01-2024 02:00 - 03:00 193 MW

04-01-2024 03:00 - 04:00 193 MW

04-01-2024 04:00 - 05:00 193 MW

04-01-2024 05:00 - 06:00 232 MW

04-01-2024 06:00 - 07:00 247 MW

04-01-2024 07:00 - 08:00 255 MW

04-01-2024 08:00 - 09:00 303 MW

04-01-2024 09:00 - 10:00 300 MW

04-01-2024 10:00 - 11:00 304 MW

04-01-2024 11:00 - 12:00 313 MW

04-01-2024 12:00 - 13:00 304 MW

04-01-2024 13:00 - 14:00 313 MW

04-01-2024 14:00 - 15:00 316 MW

04-01-2024 15:00 - 16:00 303 MW

04-01-2024 16:00 - 17:00 304 MW

04-01-2024 17:00 - 18:00 313 MW

04-01-2024 18:00 - 19:00 303 MW

04-01-2024 19:00 - 20:00 313 MW

04-01-2024 20:00 - 21:00 300 MW

04-01-2024 21:00 - 22:00 313 MW

04-01-2024 22:00 - 23:00 313 MW

04-01-2024 23:00 - 24:00 327 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication