Capacity Curtailment on the IF2 border for delivery 02-02-2024 to 21-02-2024
- TSO(s) *:
National Grid IFA 2 Limited (NGIFA2) and RTE EDF Transport S.A. (RTE)
- Identification of affected Long Term Transmission Rights
IFA2 FR>GB
IFA2 GB>FR
- Triggering event :
Curtailment to ensure operation remains within Operational Security Limits
- Affected volume in MW / hour for each concerned period :
02/02/2024 – 21/02/2024
00:00 - 01:00 675
01:00 - 02:00 675
02:00 - 03:00 675
03:00 - 04:00 675
04:00 - 05:00 675
05:00 - 06:00 675
06:00 - 07:00 675
07:00 - 08:00 675
08:00 - 09:00 675
09:00 - 10:00 675
10:00 - 11:00 675
11:00 - 12:00 675
12:00 - 13:00 675
13:00 - 14:00 675
14:00 - 15:00 675
15:00 - 16:00 675
16:00 - 17:00 675
17:00 - 18:00 675
18:00 - 19:00 675
19:00 - 20:00 675
20:00 - 21:00 675
21:00 - 22:00 675
22:00 - 23:00 675
23:00 - 00:00 675
- Amount of LTTR remaining after curtailment :
02/02/2024 – 21/02/2024
00:00 - 01:00 0
01:00 - 02:00 0
02:00 - 03:00 0
03:00 - 04:00 0
04:00 - 05:00 0
05:00 - 06:00 0
06:00 - 07:00 0
07:00 - 08:00 0
08:00 - 09:00 0
09:00 - 10:00 0
10:00 - 11:00 0
11:00 - 12:00 0
12:00 - 13:00 0
13:00 - 14:00 0
14:00 - 15:00 0
15:00 - 16:00 0
16:00 - 17:00 0
17:00 - 18:00 0
18:00 - 19:00 0
19:00 - 20:00 0
20:00 - 21:00 0
21:00 - 22:00 0
22:00 - 23:00 0
23:00 - 00:00 0
- Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Thermal Limits
- Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
Capacity limitation due to unplanned maintenance