Capacity Curtailment on the FR-CH border for delivery 20-03-2024
1. TSO(s)*:
RTE, SWISSGRID
2. Identification of affected Long Term Transmission Rights:
FR-CH
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
20-03-2024 00:00 - 01:00 947 MW
20-03-2024 01:00 - 02:00 947 MW
20-03-2024 02:00 - 03:00 947 MW
20-03-2024 03:00 - 04:00 947 MW
20-03-2024 04:00 - 05:00 947 MW
20-03-2024 05:00 - 06:00 947 MW
20-03-2024 06:00 - 07:00 947 MW
20-03-2024 07:00 - 08:00 947 MW
20-03-2024 08:00 - 09:00 947 MW
20-03-2024 09:00 - 10:00 947 MW
20-03-2024 10:00 - 11:00 947 MW
20-03-2024 11:00 - 12:00 947 MW
20-03-2024 12:00 - 13:00 947 MW
20-03-2024 13:00 - 14:00 947 MW
20-03-2024 14:00 - 15:00 947 MW
20-03-2024 15:00 - 16:00 947 MW
20-03-2024 16:00 - 17:00 947 MW
20-03-2024 17:00 - 18:00 947 MW
20-03-2024 18:00 - 19:00 947 MW
20-03-2024 19:00 - 20:00 947 MW
20-03-2024 20:00 - 21:00 947 MW
20-03-2024 21:00 - 22:00 947 MW
20-03-2024 22:00 - 23:00 947 MW
20-03-2024 23:00 - 24:00 947 MW
5. Amount of LTTR remaining after curtailment:
20-03-2024 00:00 - 01:00 579 MW
20-03-2024 01:00 - 02:00 579 MW
20-03-2024 02:00 - 03:00 579 MW
20-03-2024 03:00 - 04:00 579 MW
20-03-2024 04:00 - 05:00 579 MW
20-03-2024 05:00 - 06:00 579 MW
20-03-2024 06:00 - 07:00 579 MW
20-03-2024 07:00 - 08:00 579 MW
20-03-2024 08:00 - 09:00 579 MW
20-03-2024 09:00 - 10:00 579 MW
20-03-2024 10:00 - 11:00 579 MW
20-03-2024 11:00 - 12:00 579 MW
20-03-2024 12:00 - 13:00 579 MW
20-03-2024 13:00 - 14:00 579 MW
20-03-2024 14:00 - 15:00 579 MW
20-03-2024 15:00 - 16:00 579 MW
20-03-2024 16:00 - 17:00 579 MW
20-03-2024 17:00 - 18:00 579 MW
20-03-2024 18:00 - 19:00 579 MW
20-03-2024 19:00 - 20:00 579 MW
20-03-2024 20:00 - 21:00 579 MW
20-03-2024 21:00 - 22:00 579 MW
20-03-2024 22:00 - 23:00 579 MW
20-03-2024 23:00 - 24:00 579 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment:
Network Security
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)?
The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits