Capacity Curtailment on the CH-IT border for delivery 08-04-2024
Published:
1. TSO(s)*:
SWISSGRID
2. Identification of affected Long Term Transmission Rights:
CH-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Estimated duration and affected volume in MW / hour for each concerned period:
08-04-2024 12:00 - 13:00 2857 MW
08-04-2024 13:00 - 14:00 2857 MW
5. Estimated duration and amount of LTTR remaining after curtailment:
08-04-2024 12:00 - 13:00 2762 MW
08-04-2024 13:00 - 14:00 2762 MW