Capacity Curtailment on the FR-IT border for delivery 18-04-2024

Published:

1. TSO(s)*:

2. Identification of affected Long Term Transmission Rights:

FR-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

18-04-2024 07:00 - 08:00 1604 MW

18-04-2024 08:00 - 09:00 1604 MW

18-04-2024 13:00 - 14:00 1604 MW

18-04-2024 15:00 - 16:00 1604 MW

18-04-2024 16:00 - 17:00 1604 MW

18-04-2024 17:00 - 18:00 1604 MW

18-04-2024 23:00 - 24:00 1604 MW

5. Amount of LTTR remaining after curtailment:

18-04-2024 07:00 - 08:00 1390 MW

18-04-2024 08:00 - 09:00 1390 MW

18-04-2024 13:00 - 14:00 1549 MW

18-04-2024 15:00 - 16:00 1431 MW

18-04-2024 16:00 - 17:00 1431 MW

18-04-2024 17:00 - 18:00 1431 MW

18-04-2024 23:00 - 24:00 1391 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.

 

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication

JAO Operations Team