Capacity Curtailment on the CH-IT border for delivery period 14-08-2024
1. TSO(s)*:
SWISSGRID
2. Identification of affected Long Term Transmission Rights:
CH-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
14-08-2024 08:00 - 09:00 1381 MW
14-08-2024 09:00 - 10:00 1381 MW
14-08-2024 10:00 - 11:00 1381 MW
14-08-2024 11:00 - 12:00 1381 MW
14-08-2024 12:00 - 13:00 1381 MW
14-08-2024 13:00 - 14:00 1381 MW
14-08-2024 14:00 - 15:00 1381 MW
14-08-2024 15:00 - 16:00 1381 MW
14-08-2024 16:00 - 17:00 1381 MW
14-08-2024 17:00 - 18:00 1381 MW
14-08-2024 18:00 - 19:00 1381 MW
14-08-2024 19:00 - 20:00 1381 MW
5. Amount of LTTR remaining after curtailment:
14-08-2024 08:00 - 09:00 1207 MW
14-08-2024 09:00 - 10:00 1167 MW
14-08-2024 10:00 - 11:00 1167 MW
14-08-2024 11:00 - 12:00 1167 MW
14-08-2024 12:00 - 13:00 1207 MW
14-08-2024 13:00 - 14:00 1207 MW
14-08-2024 14:00 - 15:00 1125 MW
14-08-2024 15:00 - 16:00 1125 MW
14-08-2024 16:00 - 17:00 1125 MW
14-08-2024 17:00 - 18:00 1167 MW
14-08-2024 18:00 - 19:00 1155 MW
14-08-2024 19:00 - 20:00 1098 MW