Capacity Curtailment on the CH-IT border for delivery period 26-08-2025

Published:

1. TSO(s)*:

SWISSGRID

2. Identification of affected Long Term Transmission Rights:

CH-IT

3. Triggering event:

Curtailment due to Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

26-08-2025 09:00 - 10:00 1497 MW

26-08-2025 10:00 - 11:00 1497 MW

26-08-2025 11:00 - 12:00 1497 MW

5. Amount of LTTR remaining after curtailment:

26-08-2025 09:00 - 10:00 1159 MW

26-08-2025 10:00 - 11:00 1159 MW

26-08-2025 11:00 - 12:00 1159 MW