Capacity Curtailment on the AT-DE border for delivery period 20-09-2025
1. TSO(s)*:
APG
2. Identification of affected Long Term Transmission Rights:
AT-DE
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
20-09-2025 10:00 - 11:00 3819 MW
20-09-2025 11:00 - 12:00 3819 MW
20-09-2025 12:00 - 13:00 3819 MW
20-09-2025 13:00 - 14:00 3819 MW
20-09-2025 14:00 - 15:00 3819 MW
20-09-2025 15:00 - 16:00 3819 MW
5. Amount of LTTR remaining after curtailment:
20-09-2025 10:00 - 11:00 485 MW
20-09-2025 11:00 - 12:00 756 MW
20-09-2025 12:00 - 13:00 904 MW
20-09-2025 13:00 - 14:00 1264 MW
20-09-2025 14:00 - 15:00 1345 MW
20-09-2025 15:00 - 16:00 1274 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?