Capacity Curtailment on the FR-CH border for delivery period 12-10-2025
1. TSO(s)*:
RTE, SWISSGRID
2. Identification of affected Long Term Transmission Rights:
FR-CH
3. Triggering event:
Curtailment due to Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
12-10-2025 09:00 - 10:00 369 MW
12-10-2025 10:00 - 11:00 369 MW
12-10-2025 11:00 - 12:00 369 MW
12-10-2025 12:00 - 13:00 369 MW
12-10-2025 13:00 - 14:00 369 MW
12-10-2025 14:00 - 15:00 369 MW
12-10-2025 15:00 - 16:00 369 MW
12-10-2025 16:00 - 17:00 369 MW
5. Amount of LTTR remaining after curtailment:
12-10-2025 09:00 - 10:00 0 MW
12-10-2025 10:00 - 11:00 0 MW
12-10-2025 11:00 - 12:00 0 MW
12-10-2025 12:00 - 13:00 0 MW
12-10-2025 13:00 - 14:00 0 MW
12-10-2025 14:00 - 15:00 0 MW
12-10-2025 15:00 - 16:00 0 MW
12-10-2025 16:00 - 17:00 0 MW