Capacity Curtailment on the IT-SI border for delivery period 16-10-2025

Published:

1. TSO(s)*:

TERNA

2. Identification of affected Long Term Transmission Rights:

IT-SI

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

16-10-2025 18:00 - 19:00 334 MW

16-10-2025 19:00 - 20:00 334 MW

16-10-2025 20:00 - 21:00 334 MW

5. Amount of LTTR remaining after curtailment:

16-10-2025 18:00 - 19:00 0 MW

16-10-2025 19:00 - 20:00 0 MW

16-10-2025 20:00 - 21:00 0 MW


6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
 
Expected violation of operational security limits of physical transmission assets
 
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation