Capacity Curtailment on the EE-LV border for delivery period 06/11/2025
1. TSO(s)*:
ELERING
2. Identification of affected Long Term Transmission Rights:
EE-LV
3, Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / period:
06-11-2025 00:00 - 01:00 550 MW
06-11-2025 01:00 - 02:00 550 MW
06-11-2025 02:00 - 03:00 550 MW
06-11-2025 03:00 - 04:00 550 MW
06-11-2025 17:00 - 18:00 550 MW
06-11-2025 18:00 - 19:00 550 MW
06-11-2025 19:00 - 20:00 550 MW
5. Amount of LTTR remaining after curtailment:
06-11-2025 00:00 - 01:00 494 MW
06-11-2025 01:00 - 02:00 493 MW
06-11-2025 02:00 - 03:00 494 MW
06-11-2025 03:00 - 04:00 491 MW
06-11-2025 17:00 - 18:00 500 MW
06-11-2025 18:00 - 19:00 505 MW
06-11-2025 19:00 - 20:00 511 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
https://umm.nordpoolgroup.com/#/messages?publicationDate=all&eventDate=custom&connections=EE-LV&eventDateStart=1970-01-01&eventDateStop=2125-04-20 , as well as the capacity already allocated on the Baltic Balancing Market for balancing capacity sharing at https://baltic.transparency-dashboard.eu/node/108
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
There is no alternative to the curtailment of the affected LTTRs.