Capacity Curtailment on the AT-IT border for delivery period 04-01-2026
1. TSO(s)*:
TERNA
2. Identification of affected Long Term Transmission Rights:
AT-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
04-01-2026 15:00 - 16:00 224 MW
04-01-2026 16:00 - 17:00 224 MW
04-01-2026 17:00 - 18:00 224 MW
04-01-2026 18:00 - 19:00 224 MW
04-01-2026 19:00 - 20:00 224 MW
04-01-2026 20:00 - 21:00 224 MW
5. Amount of LTTR remaining after curtailment:
04-01-2026 15:00 - 16:00 115 MW
04-01-2026 16:00 - 17:00 115 MW
04-01-2026 17:00 - 18:00 115 MW
04-01-2026 18:00 - 19:00 111 MW
04-01-2026 19:00 - 20:00 111 MW
04-01-2026 20:00 - 21:00 111 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC