Capacity Curtailment on the FR-IT border for delivery period 19-01-2026
1. TSO(s)*:
TERNA, RTE
2. Identification of affected Long Term Transmission Rights:
FR-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
19-01-2026 09:00 - 10:00 2600 MW
19-01-2026 10:00 - 11:00 2600 MW
19-01-2026 11:00 - 12:00 2600 MW
19-01-2026 21:00 - 22:00 2600 MW
19-01-2026 22:00 - 23:00 2600 MW
19-01-2026 23:00 - 24:00 2600 MW
5. Amount of LTTR remaining after curtailment:
19-01-2026 09:00 - 10:00 2458 MW
19-01-2026 10:00 - 11:00 2458 MW
19-01-2026 11:00 - 12:00 2458 MW
19-01-2026 21:00 - 22:00 2441 MW
19-01-2026 22:00 - 23:00 2441 MW
19-01-2026 23:00 - 24:00 2286 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC.
*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication