Capacity Curtailment on the IT-FR border for delivery period 20-01-2026

Published:

1. TSO(s)*:

TERNA

2. Identification of affected Long Term Transmission Rights:

IT-FR

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

20-01-2026 05:00 - 06:00 1495 MW

20-01-2026 06:00 - 07:00 1495 MW

20-01-2026 07:00 - 08:00 1495 MW

20-01-2026 08:00 - 09:00 1495 MW

20-01-2026 09:00 - 10:00 1495 MW

20-01-2026 10:00 - 11:00 1495 MW

20-01-2026 11:00 - 12:00 1495 MW

20-01-2026 13:00 - 14:00 1495 MW

20-01-2026 14:00 - 15:00 1495 MW

20-01-2026 15:00 - 16:00 1495 MW

20-01-2026 16:00 - 17:00 1495 MW

20-01-2026 17:00 - 18:00 1495 MW

20-01-2026 18:00 - 19:00 1495 MW

20-01-2026 19:00 - 20:00 1495 MW

20-01-2026 20:00 - 21:00 1495 MW

20-01-2026 21:00 - 22:00 1495 MW

5. Amount of LTTR remaining after curtailment:

20-01-2026 05:00 - 06:00 1422 MW

20-01-2026 06:00 - 07:00 804 MW

20-01-2026 07:00 - 08:00 176 MW

20-01-2026 08:00 - 09:00 176 MW

20-01-2026 09:00 - 10:00 176 MW

20-01-2026 10:00 - 11:00 788 MW

20-01-2026 11:00 - 12:00 1400 MW

20-01-2026 13:00 - 14:00 1400 MW

20-01-2026 14:00 - 15:00 788 MW

20-01-2026 15:00 - 16:00 176 MW

20-01-2026 16:00 - 17:00 176 MW

20-01-2026 17:00 - 18:00 176 MW

20-01-2026 18:00 - 19:00 176 MW

20-01-2026 19:00 - 20:00 176 MW

20-01-2026 20:00 - 21:00 802 MW

20-01-2026 21:00 - 22:00 1400 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC