1. TSO(s)*:
ESO
2. Identification of affected Long Term Transmission Rights:
RO-BG
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
30-03-2024 11:00 - 12:00 1560 MW
30-03-2024 12:00 - 13:00 1560 MW
30-03-2024 13:00 - 14:00 1560 MW
30-03-2024 14:00 - 15:00 1560 MW
5. Amount of LTTR remaining after curtailment:
30-03-2024 11:00 - 12:00 480 MW
30-03-2024 12:00 - 13:00 480 MW
30-03-2024 13:00 - 14:00 480 MW
30-03-2024 14:00 - 15:00 480 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected extremely low demand which leads to lack of reserve capacity, low system stability and inertia and as a result requires a minimum number of power plants on the grid.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.
*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication