CAPACITY AVAILABILITY AT GREECE-ITALY INTERCONNECTION
Published:
With reference to the notice published on October 18th 2017 on this website about the unavailability of the link between Italy and Greece, TERNA and ADMIE inform market participants that the cable will be back in operation on Sunday 17th of December.
Therefore, the NTC will be restored at 500 MW starting from 0:00 of December 17th. Consequently the first daily auction will be held on December 16th.
Possible update referred to this notice will be promptly communicated by TERNA and ADMIE.