CAPACITY AVAILABILITY AT GREECE-ITALY INTERCONNECTION
Published:
With reference to the yearly maintenance of the HVDC cable on the Italian-Greek interconnection, TERNA and ADMIE inform market participants that the maintenance work will be extended until 28th June 2018 16:00 CET.
Therefore, due to the fact that the NTC is reduced to zero, no daily capacity will be allocated during the outage period on the Italy-Greece interconnection and the Joint Allocation Office (JAO) will curtail the long-term capacities already allocated, according to the Auction Rules provisions.
Possible update referred to this notice will be promptly communicated by TERNA and ADMIE.