Capacity Curtailment on AT<IT for period 15/05/2019

Published:

Dear Market Participants,

The long-term allocated capacities for delivery date 15/05/2019 on the corridor from Austria to Italy have been curtailed to ensure operation remains within Operational Security Limits.

From position 8 to position 16 it was reduced to 57 MW

On Position 17 it was reduced to 121 MW

On Position 18 it was reduced to 178 MW

The curtailment will be reflected in the rights documents.

Best regards,

Operations TEAM

Capacity Allocation Specialist

JAO S.A.