Capacity Curtailment from Austria to Italy, from Slovenia to Italy and from Germany to the Netherlands for market period 10/08/2019
Dear Market Participants,
The long-term allocated capacities for delivery date 10/08/2019 on the corridor from Austria to Italy, from Slovenia to Italy and from Germany to the Netherlands have been curtailed to ensure operation remains within Operational Security Limits.
AT>IT
On position 8 and 9 it was reduced to 180 MW
SI>IT
On position 8 and 9 it was reduced to 70 MW
DE>NL
On position 13 it was reduced to 1128
On position 14 it was reduced to 957
On position 15 it was reduced to 1023
On position 16 it was reduced to 966
On position 17 it was reduced to 929
Please consider the latest version of the programming authorizations.
Please be aware that the consequences of this reduction might only be visible in the final FB parameters publication around 09:50.
Best regards,
Operations TEAM
JAO S.A.
2 rue de Bitbourg
L-1273 Luxembourg-Hamm
T. +352 27 62 38 38