Capacity Curtailment on Austria-Italy, Slovenia-Italy, France-Italy interconnectors for 06.09.2018
Dear Market Participants,
The long-term allocated capacity for delivery date 06.09.2018 on the corridor from Austria to Italy, from Slovenia to Italy and from France to Italy have been curtailed to ensure operation remains within Operational Security Limits:
AT>IT:
From position 1 to position 3 reduced to 160 MW
From position 22 to position 23 reduced to 179 MW
On position 24 reduced to 182 MW
SI>IT:
From position 1 to position 3 reduced to 256 MW
FR>IT:
From position 1 to position 3 reduced to 1390 MW
From position 4 to position 6 reduced to 1928 MW
From position 22 to position 23 reduced to 1665 MW
On position 24 reduced to 1717 MW
Please consider the latest versions of the programming authorizations.
Best regards,
Operations Team