Capacity Curtailment on the BDL-GB<>NL border for delivery date 03/12/2021
Published:
- TSO(s) *:
BritNed Development Limited
- Identification of affected Long Term Transmission Rights
BDL GB-NL
BDL NL-GB
- Triggering event :
☒Curtailment to ensure operation remains within Operational Security Limits |
- Affected volume in MW / hour for each concerned period :
03/12/2021 12:00 – 14:00
NL-GB
- 12:00 – 14:00 – 939 MW
GB-NL
- 12:00 – 14:00 – 956 MW
- Amount of LTTR remaining after curtailment :
03/12/2021 12:00 – 14:00
NL-GB
- 12:00 – 14:00 – 0 MW
GB-NL
- 12:00 – 14:00 – 0 MW
- Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Voltage limits, short-circuit current limits, frequency and dynamic stability limits
- Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
No other re-dispatch possibilities