Capacity Curtailment on the BDL GB<>NL border for delivery days 11/12/2020 to 29/12/2020 2/2

Published:
/p>

GB-NL

14:00

15:00

0MW

GB-NL

15:00

16:00

0MW

GB-NL

16:00

17:00

0MW

GB-NL

17:00

18:00

0MW

GB-NL

18:00

19:00

0MW

GB-NL

19:00

20:00

0MW

GB-NL

20:00

21:00

0MW

GB-NL

21:00

22:00

0MW

GB-NL

22:00

23:00

0MW

GB-NL

23:00

00:00

0MW

 

 

6.       Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *: voltage limits, short-circuit current limits, frequency and dynamic stability limits

.

Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *? No other re-dispatch possibilities