Capacity Curtailment on the BDL GB<>NL border for delivery days 08/05/2021 to 18/05/2021
1. TSO(s) *
BritNed Development Limited
2. Identification of affected Long Term Transmission Rights
BDL GB-NL
BDL NL-GB
3. Triggering event :
Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period:
08 May 2021 – 18 May 2021
BDL NL-GB 08.05.2021 00:00 – 18.05.2021 00:00 - 789MW
BDL GB-NL 08.05.2021 00:00 – 18.05.2021 00:00 - 829MW
5. Amount of LTTR remaining after curtailment :
08 May 2021 – 18 May 2021
BDL NL-GB 08.05.2021 00:00 – 18.05.2021 00:00 - 0MW
BDL GB-NL 08.05.2021 00:00 – 18.05.2021 00:00 - 0MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *: N/A
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
Early investigation indicates a cable fault