Capacity Curtailment on the BDL GB<>NL border for delivery days 08/05/2021 to 18/05/2021

Published:

1. TSO(s) *

BritNed Development Limited

 

2. Identification of affected Long Term Transmission Rights


BDL GB-NL

BDL NL-GB

 

3. Triggering event :
 

Curtailment due to emergency situation

 

4. Affected volume in MW / hour for each concerned period:
 

08 May 2021 – 18 May 2021 

BDL NL-GB 08.05.2021 00:00 – 18.05.2021 00:00 - 789MW

BDL GB-NL 08.05.2021 00:00 – 18.05.2021 00:00 - 829MW

 

5.            Amount of LTTR remaining after curtailment :

 

08 May 2021 – 18 May 2021 

BDL NL-GB 08.05.2021 00:00 – 18.05.2021 00:00 - 0MW

BDL GB-NL 08.05.2021 00:00 – 18.05.2021 00:00 - 0MW

 

6.            Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *: N/A

7.            Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

Early investigation indicates a cable fault