Capacity Curtailment on the CH-DE border for delivery date 25-07-2024

Published:

1. TSO(s):

Transnet BW, SWISSGRID

2. Identification of affected Long Term Transmission Rights:

CH-DE

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Estimated duration and affected volume in MW / hour for each concerned period:

25-07-2024 07:00 - 08:00 1770 MW

25-07-2024 08:00 - 09:00 1770 MW

25-07-2024 09:00 - 10:00 1770 MW

5. Estimated duration and amount of LTTR remaining after curtailment:

25-07-2024 07:00 - 08:00 1235 MW

25-07-2024 08:00 - 09:00 1235 MW

25-07-2024 09:00 - 10:00 1235 MW