Capacity Curtailment on the CH-FR border for delivery period 11-09-2024
1. TSO(s)*:
SWISSGRID
2. Identification of affected Long Term Transmission Rights:
CH-FR
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits.
4. Affected volume in MW / hour for each concerned period:
11-09-2024 16:00 - 17:00 580 MW
11-09-2024 17:00 - 18:00 580 MW
11-09-2024 18:00 - 19:00 580 MW
11-09-2024 19:00 - 20:00 580 MW
11-09-2024 20:00 - 21:00 580 MW
11-09-2024 21:00 - 22:00 580 MW
5. Amount of LTTR remaining after curtailment:
11-09-2024 16:00 - 17:00 478 MW
11-09-2024 17:00 - 18:00 478 MW
11-09-2024 18:00 - 19:00 478 MW
11-09-2024 19:00 - 20:00 324 MW
11-09-2024 20:00 - 21:00 324 MW
11-09-2024 21:00 - 22:00 324 MW