Capacity Curtailment on the CH-FR border for delivery period 12-09-2024
1. TSO(s)*:
SWISSGRID
2. Identification of affected Long Term Transmission Rights:
CH-FR
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits.
4. Affected volume in MW / hour for each concerned period:
12-09-2024 07:00 - 08:00 580 MW
12-09-2024 08:00 - 09:00 580 MW
12-09-2024 09:00 - 10:00 580 MW
12-09-2024 10:00 - 11:00 580 MW
12-09-2024 11:00 - 12:00 580 MW
12-09-2024 12:00 - 13:00 580 MW
5. Amount of LTTR remaining after curtailment:
12-09-2024 07:00 - 08:00 526 MW
12-09-2024 08:00 - 09:00 526 MW
12-09-2024 09:00 - 10:00 526 MW
12-09-2024 10:00 - 11:00 426 MW
12-09-2024 11:00 - 12:00 426 MW
12-09-2024 12:00 - 13:00 426 MW