Capacity Curtailment on the CH-IT border for delivery 04-01-2023
Dear Market Participants,
The long-term allocated capacities for delivery date 04-01-2023 on the corridor CH-IT have been curtailed to ensure operation remains within Operational Security Limits.
04-01-2023 00:00 - 01:00 was reduced by 0.0 %
04-01-2023 01:00 - 02:00 was reduced by 3.99 %
04-01-2023 02:00 - 03:00 was reduced by 14.64 %
04-01-2023 03:00 - 04:00 was reduced by 22.02 %
04-01-2023 04:00 - 05:00 was reduced by 23.95 %
04-01-2023 05:00 - 06:00 was reduced by 9.85 %
04-01-2023 06:00 - 07:00 was reduced by 0.0 %
04-01-2023 07:00 - 08:00 was reduced by 0.0 %
04-01-2023 08:00 - 09:00 was reduced by 0.0 %
04-01-2023 09:00 - 10:00 was reduced by 0.0 %
04-01-2023 10:00 - 11:00 was reduced by 0.0 %
04-01-2023 11:00 - 12:00 was reduced by 0.0 %
04-01-2023 12:00 - 13:00 was reduced by 0.0 %
04-01-2023 13:00 - 14:00 was reduced by 0.0 %
04-01-2023 14:00 - 15:00 was reduced by 0.0 %
04-01-2023 15:00 - 16:00 was reduced by 0.0 %
04-01-2023 16:00 - 17:00 was reduced by 0.0 %
04-01-2023 17:00 - 18:00 was reduced by 0.0 %
04-01-2023 18:00 - 19:00 was reduced by 0.0 %
04-01-2023 19:00 - 20:00 was reduced by 0.0 %
04-01-2023 20:00 - 21:00 was reduced by 0.0 %
04-01-2023 21:00 - 22:00 was reduced by 0.0 %
04-01-2023 22:00 - 23:00 was reduced by 0.0 %
04-01-2023 23:00 - 24:00 was reduced by 0.0 %
Please consider the latest version of the programming authorizations.
Best regards,