Capacity Curtailment on the CH-IT border for delivery 04-05-2024

Published:

1. TSO(s)*:

SWISSGRID

2. Identification of affected Long Term Transmission Rights:

CH-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

04-05-2024 12:00 - 13:00 288 MW

04-05-2024 13:00 - 14:00 288 MW

04-05-2024 14:00 - 15:00 288 MW

5. Amount of LTTR remaining after curtailment:

04-05-2024 12:00 - 13:00 0 MW

04-05-2024 13:00 - 14:00 35 MW

04-05-2024 14:00 - 15:00 159 MW