Capacity Curtailment on the CH-IT border for delivery 10-12-2023

Published:

The long-term allocated capacities for delivery date 10-12-2023 on the corridor CH-IT  have been curtailed to ensure operation remains within Operational Security Limits.

10-12-2023 00:00 - 01:00 was reduced by 10 %

10-12-2023 01:00 - 02:00 was reduced by 10 %

10-12-2023 02:00 - 03:00 was reduced by 13 %

10-12-2023 03:00 - 04:00 was reduced by 17 %

10-12-2023 04:00 - 05:00 was reduced by 22 %

10-12-2023 05:00 - 06:00 was reduced by 19 %

10-12-2023 06:00 - 07:00 was reduced by 10 %

10-12-2023 11:00 - 12:00 was reduced by 15 %

10-12-2023 12:00 - 13:00 was reduced by 30 %

10-12-2023 13:00 - 14:00 was reduced by 32 %

10-12-2023 14:00 - 15:00 was reduced by 10 %