Capacity Curtailment on the CH-IT border for delivery 17-05-2024
1. TSO(s)*:
SWISSGRID
2. Identification of affected Long Term Transmission Rights:
CH-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Estimated duration and affected volume in MW / hour for each concerned period:
17-05-2024 00:00 - 01:00 1648 MW
17-05-2024 01:00 - 02:00 1648 MW
17-05-2024 02:00 - 03:00 1648 MW
17-05-2024 03:00 - 04:00 1648 MW
17-05-2024 04:00 - 05:00 1648 MW
17-05-2024 05:00 - 06:00 1648 MW
17-05-2024 06:00 - 07:00 1648 MW
17-05-2024 08:00 - 09:00 1992 MW
17-05-2024 09:00 - 10:00 1992 MW
17-05-2024 10:00 - 11:00 1992 MW
17-05-2024 11:00 - 12:00 1992 MW
17-05-2024 12:00 - 13:00 1992 MW
17-05-2024 13:00 - 14:00 1992 MW
17-05-2024 18:00 - 19:00 1992 MW
17-05-2024 19:00 - 20:00 1992 MW
17-05-2024 23:00 - 24:00 1648 MW
5. Estimated duration and amount of LTTR remaining after curtailment:
17-05-2024 00:00 - 01:00 1603 MW
17-05-2024 01:00 - 02:00 1603 MW
17-05-2024 02:00 - 03:00 1603 MW
17-05-2024 03:00 - 04:00 1603 MW
17-05-2024 04:00 - 05:00 1603 MW
17-05-2024 05:00 - 06:00 1603 MW
17-05-2024 06:00 - 07:00 1603 MW
17-05-2024 08:00 - 09:00 1846 MW
17-05-2024 09:00 - 10:00 1846 MW
17-05-2024 10:00 - 11:00 1846 MW
17-05-2024 11:00 - 12:00 1846 MW
17-05-2024 12:00 - 13:00 1583 MW
17-05-2024 13:00 - 14:00 1826 MW
17-05-2024 18:00 - 19:00 1846 MW
17-05-2024 19:00 - 20:00 1846 MW
17-05-2024 23:00 - 24:00 1563 MW
*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication