Capacity Curtailment on the CH-IT border for delivery 25-02-2024
Published:
1. TSO(s)*:
SWISSGRID
2. Identification of affected Long Term Transmission Rights:
CH-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Estimated duration and affected volume in MW / hour for each concerned period:
25-02-2024 13:00 - 14:00 1973 MW
5. Estimated duration and amount of LTTR remaining after curtailment:
25-02-2024 13:00 - 14:00 1772 MW
*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication
JAO Operations Team