Capacity Curtailment on the CH-IT border for delivery 26-01-2024

Published:

1. TSO(s)*:

SWISSGRID

2. Identification of affected Long Term Transmission Rights:

CH-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Estimated duration and affected volume in MW / hour for each concerned period:

26-01-2024 09:00 - 10:00 3297 MW

26-01-2024 10:00 - 11:00 3297 MW

26-01-2024 11:00 - 12:00 3297 MW

26-01-2024 15:00 - 16:00 3297 MW

26-01-2024 16:00 - 17:00 3297 MW

26-01-2024 17:00 - 18:00 3297 MW

5. Estimated duration and amount of LTTR remaining after curtailment:

26-01-2024 09:00 - 10:00 3098 MW

26-01-2024 10:00 - 11:00 3098 MW

26-01-2024 11:00 - 12:00 3098 MW

26-01-2024 15:00 - 16:00 3028 MW

26-01-2024 16:00 - 17:00 3063 MW

26-01-2024 17:00 - 18:00 3063 MW

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication