Capacity Curtailment on the CH-IT border for delivery 28-12-2023

Published:

1. TSO(s)*:

SWISSGRID

2. Identification of affected Long Term Transmission Rights:

CH-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Estimated duration and affected volume in MW / hour for each concerned period:

28-12-2023 00:00 - 01:00 2865 MW

28-12-2023 01:00 - 02:00 2865 MW

28-12-2023 02:00 - 03:00 2865 MW

28-12-2023 03:00 - 04:00 2865 MW

28-12-2023 04:00 - 05:00 2865 MW

28-12-2023 05:00 - 06:00 2865 MW

5. Estimated duration and amount of LTTR remaining after curtailment:

28-12-2023 00:00 - 01:00 1871 MW

28-12-2023 01:00 - 02:00 2414 MW

28-12-2023 02:00 - 03:00 2209 MW

28-12-2023 03:00 - 04:00 2209 MW

28-12-2023 04:00 - 05:00 2157 MW

28-12-2023 05:00 - 06:00 2468 MW