Capacity Curtailment on the CH-IT border for delivery 30-03-2024
1. TSO(s)*:
SWISSGRID
2. Identification of affected Long Term Transmission Rights:
CH-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Estimated duration and affected volume in MW / hour for each concerned period:
30-03-2024 07:00 - 08:00 1842 MW
30-03-2024 08:00 - 09:00 1922 MW
30-03-2024 09:00 - 10:00 1943 MW
30-03-2024 10:00 - 11:00 2390 MW
30-03-2024 11:00 - 12:00 2316 MW
30-03-2024 12:00 - 13:00 2132 MW
30-03-2024 13:00 - 14:00 1976 MW
30-03-2024 14:00 - 15:00 2160 MW
5. Estimated duration and amount of LTTR remaining after curtailment:
30-03-2024 07:00 - 08:00 1518 MW
30-03-2024 08:00 - 09:00 1844 MW
30-03-2024 09:00 - 10:00 1904 MW
30-03-2024 10:00 - 11:00 2351 MW
30-03-2024 11:00 - 12:00 2185 MW
30-03-2024 12:00 - 13:00 1756 MW
30-03-2024 13:00 - 14:00 1406 MW
30-03-2024 14:00 - 15:00 1836 MW