Capacity Curtailment on the CH-IT border for delivery date 07-07-2024

Published:

1. TSO(s):

SWISSGRID

2. Identification of affected Long Term Transmission Rights:

CH-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Estimated duration and affected volume in MW / hour for each concerned period:

07-07-2024 03:00 - 04:00 1942 MW

07-07-2024 07:00 - 08:00 1942 MW

07-07-2024 08:00 - 09:00 1942 MW

07-07-2024 09:00 - 10:00 1942 MW

07-07-2024 10:00 - 11:00 1942 MW

07-07-2024 11:00 - 12:00 1942 MW

07-07-2024 12:00 - 13:00 1942 MW

07-07-2024 13:00 - 14:00 1942 MW

07-07-2024 14:00 - 15:00 1942 MW

07-07-2024 15:00 - 16:00 1942 MW

07-07-2024 16:00 - 17:00 1942 MW

07-07-2024 17:00 - 18:00 1942 MW

07-07-2024 18:00 - 19:00 1942 MW

07-07-2024 19:00 - 20:00 1942 MW

5. Estimated duration and amount of LTTR remaining after curtailment:

07-07-2024 03:00 - 04:00 1895 MW

07-07-2024 07:00 - 08:00 1705 MW

07-07-2024 08:00 - 09:00 1345 MW

07-07-2024 09:00 - 10:00 877 MW

07-07-2024 10:00 - 11:00 528 MW

07-07-2024 11:00 - 12:00 276 MW

07-07-2024 12:00 - 13:00 0 MW

07-07-2024 13:00 - 14:00 0 MW

07-07-2024 14:00 - 15:00 0 MW

07-07-2024 15:00 - 16:00 0 MW

07-07-2024 16:00 - 17:00 118 MW

07-07-2024 17:00 - 18:00 683 MW

07-07-2024 18:00 - 19:00 1263 MW

07-07-2024 19:00 - 20:00 1825 MW