Capacity Curtailment on the CH-IT border for delivery date 13-08-2024

Published:

1. TSO(s):
SWISSGRID

2. Identification of affected Long Term Transmission Rights:
CH-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits

4. Estimated duration and affected volume in MW / hour for each concerned period:
13-08-2024 08:00 - 09:00 1381 MW
13-08-2024 09:00 - 10:00 1381 MW
13-08-2024 11:00 - 12:00 1381 MW
13-08-2024 14:00 - 15:00 1381 MW
13-08-2024 15:00 - 16:00 1381 MW
13-08-2024 16:00 - 17:00 1381 MW
13-08-2024 17:00 - 18:00 1381 MW
13-08-2024 18:00 - 19:00 1381 MW
13-08-2024 19:00 - 20:00 1381 MW

5. Estimated duration and amount of LTTR remaining after curtailment:
13-08-2024 08:00 - 09:00 1340 MW
13-08-2024 09:00 - 10:00 1340 MW
13-08-2024 11:00 - 12:00 1327 MW
13-08-2024 14:00 - 15:00 1327 MW
13-08-2024 15:00 - 16:00 1327 MW
13-08-2024 16:00 - 17:00 1291 MW
13-08-2024 17:00 - 18:00 1291 MW
13-08-2024 18:00 - 19:00 1291 MW
13-08-2024 19:00 - 20:00 1249 MW