Capacity Curtailment on the CH-IT border for delivery date 18-06-2024
1. TSO(s):
SWISSGRID
2. Identification of affected Long Term Transmission Rights:
CH-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Estimated duration and affected volume in MW / hour for each concerned period:
18-06-2024 00:00 – 01:00 1892 MW
18-06-2024 01:00 – 02: 00 1892 MW
18-06-2024 02:00-03:00 1892 MW
18-06-2024 03:00-04:00 1892 MW
18-06-2024 04:00 -05:00 1892 MW
18-06-2024 05:00 -06:00 1892 MW
18-06-2024 06:00 -07:00 1892 MW
18-06-2024 08:00 - 09:00 2092 MW
18-06-2024 09:00 - 10:00 2092 MW
18-06-2024 10:00 - 11:00 2092 MW
18-06-2024 11:00 - 12:00 2092 MW
18-06-2024 12:00 - 13:00 2092 MW
18-06-2024 13:00 - 14:00 2092 MW
18-06-2024 14:00 - 15:00 2092 MW
18-06-2024 15:00 - 16:00 2092 MW
18-06-2024 16:00 - 17:00 2092 MW
18-06-2024 17:00 - 18:00 2092 MW
18-06-2024 18:00 - 19:00 2092 MW
18-06-2024 19:00 - 20:00 2092 MW
18-06-2024 20:00-21:00 1892 MW
18-06-2024 23:00 - 24:00 1892 MW
5. Estimated duration and amount of LTTR remaining after curtailment:
18-06-2024 00:00 – 01:00 1844 MW
18-06-2024 01:00 – 02: 00 1844 MW
18-06-2024 02:00-03:00 1844MW
18-06-2024 03:00-04:00 1844 MW
18-06-2024 04:00 -05:00 1844 MW
18-06-2024 05:00 -06:00 1844 MW
18-06-2024 06:00 -07:00 1844 MW
18-06-2024 08:00 - 09:00 1905 MW
18-06-2024 09:00 - 10:00 1905 MW
18-06-2024 10:00 - 11:00 1905 MW
18-06-2024 11:00 - 12:00 1905 MW
18-06-2024 12:00 - 13:00 1905 MW
18-06-2024 13:00 - 14:00 1905 MW
18-06-2024 14:00 - 15:00 1905 MW
18-06-2024 15:00 - 16:00 1819 MW
18-06-2024 16:00 - 17:00 1819 MW
18-06-2024 17:00 - 18:00 1819 MW
18-06-2024 18:00 - 19:00 1819 MW
18-06-2024 19:00 - 20:00 1819 MW
18-06-2024 20:00-21:00 1829 MW
18-06-2024 23:00 - 24:00 1809 MW