Capacity Curtailment on the CH-IT border for delivery date 29-06-2024
Published:
1. TSO(s):
SWISSGRID
2. Identification of affected Long Term Transmission Rights:
CH-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Estimated duration and affected volume in MW / hour for each concerned period:
29-06-2024 12:00 - 13:00 1360 MW
5. Estimated duration and amount of LTTR remaining after curtailment:
29-06-2024 12:00 - 13:00 1145 MW