Capacity Curtailment on the CH-IT border for delivery date 31-07-2024
1. TSO(s):
SWISSGRID
2. Identification of affected Long Term Transmission Rights:
CH-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Estimated duration and affected volume in MW / hour for each concerned period:
31-07-2024 15:00 - 16:00 2442 MW
31-07-2024 16:00 - 17:00 2442 MW
31-07-2024 17:00 - 18:00 2442 MW
31-07-2024 18:00 - 19:00 2442 MW
31-07-2024 19:00 - 20:00 2442 MW
5. Estimated duration and amount of LTTR remaining after curtailment:
31-07-2024 15:00 - 16:00 2338 MW
31-07-2024 16:00 - 17:00 2338 MW
31-07-2024 17:00 - 18:00 2338 MW
31-07-2024 18:00 - 19:00 2362 MW
31-07-2024 19:00 - 20:00 2362 MW