Capacity Curtailment on the CH-IT border for delivery period 25-08-2024
Published:
1. TSO(s)*:
SWISSGRID
2. Identification of affected Long Term Transmission Rights:
CH-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
25-08-2024 11:00 - 12:00 682 MW
25-08-2024 12:00 - 13:00 682 MW
25-08-2024 13:00 - 14:00 682 MW
25-08-2024 14:00 - 15:00 682 MW
25-08-2024 15:00 - 16:00 682 MW
5. Amount of LTTR remaining after curtailment:
25-08-2024 11:00 - 12:00 208 MW
25-08-2024 12:00 - 13:00 0 MW
25-08-2024 13:00 - 14:00 0 MW
25-08-2024 14:00 - 15:00 0 MW
25-08-2024 15:00 - 16:00 309 MW