Capacity Curtailment on the CH-IT border for delivery period 25-12-2025

Published:

1. TSO(s)*:

SWISSGRID

2. Identification of affected Long Term Transmission Rights:

CH-IT

3. Triggering event:

Curtailment due to Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

25-12-2025 03:00 - 04:00 1083 MW

25-12-2025 04:00 - 05:00 1083 MW

25-12-2025 05:00 - 06:00 1083 MW

25-12-2025 06:00 - 07:00 1083 MW

25-12-2025 07:00 - 08:00 1083 MW

25-12-2025 10:00 - 11:00 1083 MW

25-12-2025 11:00 - 12:00 1083 MW

25-12-2025 12:00 - 13:00 1083 MW

25-12-2025 13:00 - 14:00 1083 MW

25-12-2025 14:00 - 15:00 1083 MW

25-12-2025 15:00 - 16:00 1083 MW

25-12-2025 16:00 - 17:00 1083 MW

5. Amount of LTTR remaining after curtailment:

25-12-2025 03:00 - 04:00 989 MW

25-12-2025 04:00 - 05:00 946 MW

25-12-2025 05:00 - 06:00 946 MW

25-12-2025 06:00 - 07:00 946 MW

25-12-2025 07:00 - 08:00 1021 MW

25-12-2025 10:00 - 11:00 1021 MW

25-12-2025 11:00 - 12:00 1021 MW

25-12-2025 12:00 - 13:00 1021 MW

25-12-2025 13:00 - 14:00 1021 MW

25-12-2025 14:00 - 15:00 1021 MW

25-12-2025 15:00 - 16:00 1021 MW

25-12-2025 16:00 - 17:00 1021 MW