Capacity Curtailment on the CH-IT border for delivery period 03-01-2026

Published:

1. TSO(s)*:

SWISSGRID

2. Identification of affected Long Term Transmission Rights:

CH-IT

3. Triggering event:

Curtailment due to Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

03-01-2026 02:00 - 03:00 2349 MW

03-01-2026 03:00 - 04:00 2349 MW

03-01-2026 04:00 - 05:00 2349 MW

03-01-2026 05:00 - 06:00 2349 MW

03-01-2026 06:00 - 07:00 2349 MW

03-01-2026 07:00 - 08:00 2349 MW

5. Amount of LTTR remaining after curtailment:

03-01-2026 02:00 - 03:00 1762 MW

03-01-2026 03:00 - 04:00 1011 MW

03-01-2026 04:00 - 05:00 1011 MW

03-01-2026 05:00 - 06:00 1011 MW

03-01-2026 06:00 - 07:00 1011 MW

03-01-2026 07:00 - 08:00 1880 MW