Capacity Curtailment on the CH-IT border for delivery period 29-01-2026
1. TSO(s)*:
SWISSGRID
2. Identification of affected Long Term Transmission Rights:
CH-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
29-01-2026 09:00 - 10:00 2786 MW
29-01-2026 10:00 - 11:00 2786 MW
29-01-2026 11:00 - 12:00 2786 MW
29-01-2026 12:00 - 13:00 2786 MW
29-01-2026 13:00 - 14:00 2786 MW
29-01-2026 14:00 - 15:00 2786 MW
5. Amount of LTTR remaining after curtailment:
29-01-2026 09:00 - 10:00 2588 MW
29-01-2026 10:00 - 11:00 2588MW
29-01-2026 11:00 - 12:00 2588 MW
29-01-2026 12:00 - 13:00 2504 MW
29-01-2026 13:00 - 14:00 2504 MW
29-01-2026 14:00 - 15:00 2504 MW