Capacity Curtailment on the CH-IT border for delivery period 24-09-2024
1. TSO(s)*:
SWISSGRID
2. Identification of affected Long Term Transmission Rights:
CH-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Estimated duration and affected volume in MW / hour for each concerned period:
24-09-2024 08:00 - 09:00 2142 MW
24-09-2024 12:00 - 13:00 2142 MW
24-09-2024 13:00 - 14:00 2142 MW
24-09-2024 14:00 - 15:00 2142 MW
24-09-2024 18:00 - 19:00 2142 MW
24-09-2024 19:00 - 20:00 2142 MW
5. Estimated duration and amount of LTTR remaining after curtailment:
24-09-2024 08:00 - 09:00 2059 MW
24-09-2024 12:00 - 13:00 2059 MW
24-09-2024 13:00 - 14:00 2059 MW
24-09-2024 14:00 - 15:00 2059 MW
24-09-2024 18:00 - 19:00 2059 MW
24-09-2024 19:00 - 20:00 2059 MW