Capacity Curtailment on the CH-IT border for delivery period 25-09-2024
Published:
1. TSO(s):
SWISSGRID
2. Identification of affected Long Term Transmission Rights:
CH-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Estimated duration and affected volume in MW / hour for each concerned period:
25-09-2024 18:00 - 19:00 2142 MW
25-09-2024 19:00 - 20:00 2142 MW
5. Estimated duration and amount of LTTR remaining after curtailment:
25-09-2024 18:00 - 19:00 2038 MW
25-09-2024 19:00 - 20:00 2038 MW