Capacity Curtailment on the CH-IT border for delivery period 28-09-2024

Published:

1. TSO(s)*:

SWISSGRID

2. Identification of affected Long Term Transmission Rights:

CH-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Estimated duration and affected volume in MW / hour for each concerned period:

28-09-2024 11:00 - 12:00 1360 MW

28-09-2024 12:00 - 13:00 1360 MW

28-09-2024 13:00 - 14:00 1360 MW

28-09-2024 14:00 - 15:00 1360 MW

28-09-2024 15:00 - 16:00 1360 MW

28-09-2024 16:00 - 17:00 1360 MW

5. Estimated duration and amount of LTTR remaining after curtailment:

28-09-2024 11:00 - 12:00 875 MW

28-09-2024 12:00 - 13:00 356 MW

28-09-2024 13:00 - 14:00 0 MW

28-09-2024 14:00 - 15:00 0 MW

28-09-2024 15:00 - 16:00 247 MW

28-09-2024 16:00 - 17:00 1086 MW