Capacity Curtailment on the CH-IT border for delivery period 14-10-2024

Published:

1. TSO(s)*:

SWISSGRID

2. Identification of affected Long Term Transmission Rights:

CH-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Estimated duration and affected volume in MW / hour for each concerned period:

14-10-2024 01:00 - 02:00 1723 MW

14-10-2024 02:00 - 03:00 1723 MW

14-10-2024 03:00 - 04:00 1723 MW

5. Estimated duration and amount of LTTR remaining after curtailment:

14-10-2024 01:00 - 02:00 1679 MW

14-10-2024 02:00 - 03:00 1679 MW

14-10-2024 03:00 - 04:00 1679 MW