Capacity Curtailment on the CH-IT border for delivery period 27-10-2024

Published:

1. TSO(s)*:

SWISSGRID

2. Identification of affected Long Term Transmission Rights:

CH-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Estimated duration and affected volume in MW / hour for each concerned period:

27-10-2024 00:00 - 01:00 1723 MW

27-10-2024 01:00 - 02:00 1723 MW

27-10-2024 02:00 - 03:00 1723 MW

27-10-2024 02:00 - 03:00 1723 MW

27-10-2024 03:00 - 04:00 1723 MW

27-10-2024 04:00 - 05:00 1723 MW

27-10-2024 05:00 - 06:00 1723 MW

27-10-2024 07:00 - 08:00 1723 MW

27-10-2024 08:00 - 09:00 1723 MW

27-10-2024 09:00 - 10:00 1723 MW

27-10-2024 10:00 - 11:00 1723 MW

27-10-2024 11:00 - 12:00 1723 MW

27-10-2024 12:00 - 13:00 1723 MW

27-10-2024 13:00 - 14:00 1723 MW

27-10-2024 14:00 - 15:00 1723 MW

5. Estimated duration and amount of LTTR remaining after curtailment:

27-10-2024 00:00 - 01:00 8 MW

27-10-2024 01:00 - 02:00 864 MW

27-10-2024 02:00 - 03:00 8 MW

27-10-2024 02:00 - 03:00 852 MW

27-10-2024 03:00 - 04:00 1499 MW

27-10-2024 04:00 - 05:00 1444 MW

27-10-2024 05:00 - 06:00 1581 MW

27-10-2024 07:00 - 08:00 1398 MW

27-10-2024 08:00 - 09:00 1103 MW

27-10-2024 09:00 - 10:00 965 MW

27-10-2024 10:00 - 11:00 446 MW

27-10-2024 11:00 - 12:00 682 MW

27-10-2024 12:00 - 13:00 897 MW

27-10-2024 13:00 - 14:00 1207 MW

27-10-2024 14:00 - 15:00 1581 MW