Capacity Curtailment on the CH-IT border for delivery period 27-11-2024

Published:

1. TSO(s)*:
SWISSGRID

 

2. Identification of affected Long Term Transmission Rights:
CH-IT

 

3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits

 

4. Affected volume in MW / hour for each concerned period:
27-11-2024 06:00 - 07:00 1973 MW 
27-11-2024 12:00 - 13:00 2297 MW 
27-11-2024 13:00 - 14:00 2297 MW 
27-11-2024 14:00 - 15:00 2297 MW

 

5. Amount of LTTR remaining after curtailment:
27-11-2024 06:00 - 07:00 1904 MW 
27-11-2024 12:00 - 13:00 2148 MW 
27-11-2024 13:00 - 14:00 2148 MW 