Capacity Curtailment on the CH-IT border for delivery period 18-12-2024

Published:

1. TSO(s)*:

SWISSGRID

2. Identification of affected Long Term Transmission Rights:

CH-IT

3. Triggering event:

Curtailment due to Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

18-12-2024 09:00 - 10:00 2497 MW

18-12-2024 10:00 - 11:00 2497 MW

18-12-2024 11:00 - 12:00 2497 MW

5. Amount of LTTR remaining after curtailment:

18-12-2024 09:00 - 10:00 2423 MW

18-12-2024 10:00 - 11:00 2423 MW

18-12-2024 11:00 - 12:00 2423 MW